Planning
CMW
©
Planning
1.
Gather information about jobsite. See page 77.
2.
3.
Classify jobsite. See page 80.
4.
5.
Check supplies and prepare equipment. See page 95.
6.
Setting Up at Jobsite
1.
2.
Unload drilling unit from trailer. See page 109.
3.
Assemble drill string. See page 117.
4.
Position drilling unit and frame. See page 113.
5.
Assemble strike system. See page 146.
6.
Anchor drilling unit. See page 135.
7.
Connect fluid system. See page 113.
8.
Calibrate tracker with beacon that will be installed in beacon housing. See tracker operator’s manual.