Jt30 /jt30 all terrain operator’s manual – Ditch Witch JT30AT User Manual
Page 163
Systems and Equipment - 163
JT30 /JT30 All Terrain Operator’s Manual
Pipeloader
CMW
Remove Single Pipe
Unload drill pipe loaded with auxiliary pipe
loaders.
1.
Ensure pipe guide is still installed and not
in storage position.
2.
Ensure pipe box is positioned properly.
See “Remove/Install Pipe Box” on
page 156.
3.
Move shuttles out half way (45°).
4.
Pull pin (3) from slot (A) on shuttle, rotate
auxiliary pipe loader (2) down, and install
pin in slot (B).
5.
Repeat step 4 for rear auxiliary pipe loader.
6.
Raise pipe.
7.
Move shuttle in, auxiliary pipe loaders should be beneath pipe column.
8.
Lower pipe into auxiliary pipe loaders.
9.
Move shuttle out (shuttle stop switch will stop shuttle movement at correct position for removing pipe).
10. Remove pipe from auxiliary pipe loaders and store properly.
11. Repeat steps 6-9 to unload remaining added drill pipe.
12. After all added drill pipe is unloaded with auxiliary pipe loaders:
•
Close both auxiliary pipe loaders. Pins must be inserted in slot (A) and held in place with retaining
pins.
•
Place pipe guide in storage position (shown) and secure in place with retaining pins.
•
Step away from pipeloader.
•
Finish loading remaining drill pipe using standard procedure.
•
If shuttle will not retract after completing single pipe operations, hold retract pipe shuttle switch and
momentarily press multi-use button to reset shuttles to normal operation (shuttles will retract).
Crushing weight. If load falls or moves it could kill or crush you.
Use proper procedures and equipment or stay away.