Delete sdcc, Dlp-e189 provision line dcc terminations – Cisco 15600 User Manual
Page 70
17-70
Cisco ONS 15600 Procedure Guide, R8.0
Chapter 17 DLPs E100 to E199
DLP- E189 Provision Line DCC Terminations
•
OOS,MT—Puts the circuit cross-connects in the OOS-MA,MT service state. This service state does
not interrupt traffic flow and allows loopbacks to be performed on the circuit, but suppresses alarms
and conditions. Use the OOS,MT administrative state for circuit testing or to suppress circuit alarms
temporarily. Change the administrative state to IS, OOS, or IS,AINS when testing is complete.
Note
Alternatively, you can choose the circuit on the Circuits tab, click the Edit button, then click the
State tab on the Edit Circuits window.
For additional information about circuit service states, refer to the “Circuits and Tunnels” chapter in the
Cisco ONS 15600 Reference Manual.
Step 6
If you want to apply the state to the circuit source and destination ports, check the Apply to Drop Ports
check box.
Note
CTC will not allow you to change a drop port service state from IS-NR to OOS-MA,DSBLD.
You must first change a port to the OOS-MA,MT service state before putting it in the
OOS-MA,DSBLD service state.
Step 7
Click Apply.
Step 8
If the Apply to Ports Results dialog box appears, view the results and click OK.
CTC will not change the service state of the circuit source and destination port in certain circumstances.
For example, if a port is in loopback (OOS-MA,LPBK & MT), CTC will not change the port to IS-NR.
In another example, if the circuit size is smaller than the port, CTC will not change the port service state
from IS-NR to OOS-MA,DSBLD. If CTC cannot change the port service state, you must change the port
service state manually. For more information, see the
“DLP-E115 Change the Service State for a Port”
Step 9
Return to your originating procedure (NTP).
DLP-E189 Provision Line DCC Terminations
Purpose
This task creates the LDCC terminations required for alarms,
administration, data, signal control information, and messages. In this task,
you can also set up the node so that it has direct IP access to a far-end
non-ONS node over the DCC network.
Tools/Equipment
None
Prerequisite Procedures
DLP-E26 Log into CTC, page 16-33
Required/As Needed
As needed
Onsite/Remote
Onsite or remote
Security Level
Provisioning or higher