3n-4010hda installation, 3n: install wsmbs – Great Plains NTA3510 Installation Instructions User Manual
Page 4

Great Plains Mfg., Inc.
4
Blockage Monitor Kits
168-414M
10/29/2008
3N-4010HDA Installation
This installation requires one of the following kits:
168-411A
3N4010HDA-6675 (66 row, 7.5in)
3N4010HDA-4810 (48 row, 10in)
If installation is being done on a new 3N-4010HDA, use
the instructions in the 196-444Q Pre-Delivery manual.
The instructions in this manual (168-414M) presume a
drill originally delivered and setup without blockage.
Additional installation information is found in the
DICKEY-john IntelliAg Air Cart Control Operator’s man-
ual.
Note: The DICKEY-john manual has only general har-
ness routing for the Great Plains air drills, and
some cable part numbers are slightly different from
those in the kits.
Refer to Figure 4 and Figure 5
9.
Select six (6):
At each tower, remove the nuts
and lock washers
at the lower U-Bolt
, and mount the plate
.
Plate orientation is small holes to top, and:
on Towers 1 & 6: extension to drill center
on Towers 2 & 5: extension away from drill center
on Towers 3 & 4: extension to drill rear
3N: Install WSMBs
Start with the left tower (Tower 1).
Refer to Figure 4 and Figure 5
10. Select one:
INTAG WSMB/FLW MNTR MODULE 18R
and two sets:
802-224C HHCS 1/4-20X1 1/4 GR5
804-006C WASHER LOCK SPRING 1/4 PLT
803-006C NUT HEX 1/4-20 PLT
Mount the WSMB
with the connector ports down.
11. Repeat step 10 for the remaining towers.
The WSMB orientation is:
on Wing towers (
connectors down, module to front
on Center towers (
connectors down, module to center
Figure 4: 3N:
Tower 2 Module Mount
27058
3
2
1
Figure 5: 3N
Tower 3 Module Mount
28182
12