3.25 Complete the Installation
1. Remove the cap from the coolant tank. Fill the coolant tank to the level shown, with Thermal Dynamics
coolant. The coolant level is visible through the translucent coolant tank. The amount of coolant required
varies with torch leads length.
Coolant Capabilities
Cat. Number and Mixture
Mixture
Protects To
7-3580 ‘Extra-CoolTM’
25 / 75
10° F / -12° C
7-3581 ‘Ultra-CoolTM’
50 / 50
27° F / -33° C
7-3582 ‘Extreme CoolTM’
Concentrate*
-65° F / -51° C
* For mixing with D-I CoolTM 7-3583
Art # A-11536
Fill Range
Coolant Tank
2. After the complete system has been installed, check that the coolant has been pumped through the system