2.1 Setting up the instrument
753 Suppressor Module / 8.753.1003 Instructions for Use
7
2
Installation
2.1
Setting up the instrument
2.1.1
Packaging
The 753 Suppressor Module is supplied together with the separately
packed accessories in special packagings containing shock-absorbing
foam linings designed to provide excellent protection. The actual in-
strument is packed in an evacuated polyethylene bag to prevent the in-
gress of dust. Please store all these special packagings as only they
can assure damage-free transport of the instrument.
2.1.2
Check
After receipt, immediately check whether the shipment is complete and
has arrived without damage (compare with delivery note and list of
accessories in section 5.2). In the case of transport damage, see
instructions in section 5.4.1 "Warranty".
2.1.3
Location
Position the instruments in the laboratory at a location convenient for
operation, free from vibrations and protected against a corrosive
atmosphere and contamination by chemicals.
2.1.4
Arrangement of the instruments
The best position for the 753 Suppressor Module is beside the 690 Ion
Chromatograph and below the 709 IC Pump.
The 753 Suppressor Module should always be placed at the bottom
of the instrument stack so that any leaks which may occur in the
pump tubing or connections cannot cause damage to the other
instruments by leakage of corrosive liquids (e.g. H
2
SO
4
).