Roller screed assembly – Multiquip WRS5200 (ORIGINAL COPY) User Manual
Page 43
wrs5200 hydraulic roller screed • operaTion manual — rev. #1 (10/22/10) — page 43
rOller ScreeD aSSeMblY
Task 11: strike Tube control cable
The following instructions illustrate the installation of the
strike tube control cable. Depending on the length of the
screed there are two lengths of cables to choose from. A
16 ft. (4.87 meters) and a 50 ft. (15.24 meters).
The control cable (Figure 30) should already be connected
to the strike tube speed and direction control lever which
can be located at the operator's platform.
The other end of the control cable should be laying inside
the trusses waiting to be connected to the hydraulic pump
lever located at the power unit end of the screed.
1. Locate cable mount bracket as referenced in Figure 30.
2. Insert the bracket onto threaded stud which is welded
to power unit. Secure bracket with washer and wing-nut.
Tighten securely.
3. Take free end of control cable and insert ball socket
onto pump lever ball stud.
4. If installing a control cable of a different length, remove
the ball socket end of the control cable from the ball
stud.
5. Next, loosen the two 10-32 nuts that secure the control
cable to the frame at the operator's platform.
6. Remove the 10-32 HHC screw and nyloc nut that
secures the rod end to the control lever.
7. Install new control cable in reverse order.
Figure 30. Strike Tube Control Cable Installation