rOller ScreeD aSSeMblY

Task 11: strike Tube control cable

The following instructions illustrate the installation of the

strike tube control cable. Depending on the length of the

screed there are two lengths of cables to choose from. A

16 ft. (4.87 meters) and a 50 ft. (15.24 meters).
The control cable (Figure 30) should already be connected

to the strike tube speed and direction control lever which

can be located at the operator's platform.
The other end of the control cable should be laying inside

the trusses waiting to be connected to the hydraulic pump

lever located at the power unit end of the screed.
1. Locate cable mount bracket as referenced in Figure 30.
2. Insert the bracket onto threaded stud which is welded

to power unit. Secure bracket with washer and wing-nut.

Tighten securely.

3. Take free end of control cable and insert ball socket

onto pump lever ball stud.

4. If installing a control cable of a different length, remove

the ball socket end of the control cable from the ball

stud.

5. Next, loosen the two 10-32 nuts that secure the control

cable to the frame at the operator's platform.

6. Remove the 10-32 HHC screw and nyloc nut that

secures the rod end to the control lever.

7. Install new control cable in reverse order.

Figure 30. Strike Tube Control Cable Installation