Oxygen Analyzer

Part II: Analysis Unit

Part II: 3-7

Figure 3-6: FET Series Resistance

3.5

Installing the Micro-Fuel Cell

The Micro-Fuel Cell is not installed in the cell block when the

instrument is shipped. It must be installed during initial installation.

Once it is expended, or if the cell is exposed to air for too long, the

Micro-Fuel Cell will need to be replaced. The cell could also require replace-
ment if the instrument has been idle for too long.

When the micro-Fuel Cell needs to be installed or replaced, follow the

procedures in chapter 5, Maintenance, for removing and installing cells.

3.6

Testing the System

After The Control Unit and the Analysis Unit are both installed and

interconnected, and the system gas and electrical connections are complete,
the system is ready to test. Before plugging either of the units into their
respective power sources:

Check the integrity and accuracy of the gas connections. Make
sure there are no leaks.

Check the integrity and accuracy of the electrical connections.
Make sure there are no exposed conductors

Check that sample pressure is between 3 and 40 psig, according
to the requirements of your process.

Power up the system, and test it as follows:

1. Repeat the Self-Diagnostic Test as described in Part I, chapter 4,

section 4.3.5.