beautypg.com

Installation – Teledyne 3010PA - Split architecture percent oxygen analyzer User Manual

Page 22

background image

Oxygen Analyzer

Part I: Control Unit

Part I: 3-1

Installation

Installation of Model 3010 Analyzers includes:

1. Unpacking, mounting, and interconnecting the Control Unit and

the Analysis Unit

2. Making gas connections to the system

3. Making electrical connections to the system

4. Testing the system.

This chapter covers installation of the Control Unit. (Installation of the

Analysis Unit is covered in Part II of this manual.)

3.1

Unpacking the Control Unit

The analyzer is shipped with all the materials you need to install and

prepare the system for operation. Carefully unpack the Control Unit and
inspect it for damage. Immediately report any damage to the shipping agent.

3.2

Mounting the Control Unit

The Model 3010PA Control Unit is for indoor use in a general purpose

area. It is NOT for hazardous environments of any type.

The standard model is designed for flush panel mounting. Figure 3-1 is

an illustration of a Model 3010 standard Control Unit front panel and mount-
ing bezel. There are four mounting holes—one in each corner of the rigid
frame. Drawing number D-64596, at the back of this manual, contains a
panel cutout diagram.

On special order, a 19" rack-mounting can be provided. Per order, one

or two 3010 series Control Units are flush-panel mounted on the 19" rack
panel. See Figure 3-2.

Figure 3-1: Front Panel of the Model 3010 Control Unit