3 - 23
To find Follower Setpoint 1 (CP-03) for Example A:
Follower E.U. desired
15
Setpoint 1
=
________________________________
=
___
=
3
Lead E.U. operation
5
15 gal/min
The Follower Engineering Units (gallon per minute) at which
you want the Follower to operate - do not confuse this with the
full capacity gal/min that the Follower is capable of pumping.
Divided by
5 gal/min
The Lead Engineering Units that the Lead is operating at - do
not confuse this with the full capacity that the Lead is capable
of operating at.
Equals
3.00
Follower Setpoint 1 (CP-03) value.
To find Follower Setpoint 2 (CP-04) for Example A:
Follower E.U. desired
22.5
Setpoint 2
=
________________________________
=
___
=
4.50
Lead E.U. operation
5
22.5 gal/min
The Follower Engineering Units (gallon per minute) at which
you want the Follower to operate - do not confuse this with the
full capacity gal/min that the Follower is capable of pumping.
Divided by
5 gal/min
The Lead Engineering Units (gallon per minute) that the Lead is
operating at - do not confuse this with the full capacity that the
Lead is capable of pumping.
Equals
4.50
Follower Setpoint 2 (CP-04) value.