beautypg.com

Local alarm test, Alarm test, continued – GE Industrial Solutions Galaxy Verification User Manual

Page 47

background image

Galaxy Power System Verification Procedures

Issue 3 January 2008

Galaxy Millennium Controller Performance Verification Procedures 3 - 3

Alarm Test, continued

Local Alarm Test

Refer to Figure 3-1 for the Millennium switch positions referred to in
this test.

Prior to performing an Alarm Test, hardware switch SW202-5 on the
BSH board must be enabled, in addition to the software switch located
at menu path:

Basic:

→ CONFIG → ALARM → TEST ALM

Intelligent:

→ CONFIG → ALARM → TEST ALM

If HVSD is desired during the test, BSH SW202-4 must also be enabled,
along with the appropriate software switch found on the front panel
under the path: MAIN

→ CONFIG → ALARM → TEST HV, and each

plant rectifier must have a load of at least 10% of its capacity.

To perform the Alarm Test from the front panel, follow the menu path:

Basic:

→ MAINT OPER → ALARM TEST

Intelligent:

→ MAINT OPER → ALARM TEST

As an alternative to the front panel configuration of the Alarm Test
software switch, it may be also configured within EasyView under the
path: CONFIGURE

→ DC PLANT → HARDWARE & SOFTWARE

CONFIGURED.

Pressing the key while the cursor is on the ALARM TEST
field will provide the message “ALARM TEST STARTED.” Use the
key to return to the MAINTENANCE OPERATION screen and
follow the relay operation in the ALARM TEST STAT: field. Pressing
while the cursor is on the ALARM TEST field will restart
the test.

Note: Front panel LEDs do not activate during the Alarm Test. the
alarms can be monitored by checking on the BSL alarm board.