GE Industrial Solutions Galaxy Verification User Manual
Page 26

Galaxy Power System Verification Procedures
2 - 14 Galaxy SC Controller Performance Verification Procedures
Issue 3 January 2008
High Float Voltage Alarm/High Voltage Shutdown Alarm
Tests, continued)
HVSD Test
Procedure for
Serial Rectifiers,
continued
Step
Action
7
Observe the following:
•
When the voltage increases to the HV (FLOAT) level the
rectifier shuts down.
•
The Green ON LED on the rectifier blinks, the ALM
LED on the rectifier is not lit.
•
After 5-6 seconds the rectifier initiates its own restart
signal again, raising the plant voltage.
•
The rectifier will shutdown and restart three additional
times.
•
Upon the fourth shutdown, the rectifier's ALM LED
lights and the rectifier's display indicates “HO.”
•
The controller receives the RFA signal from the rectifier
and initiates a restart signal 5-6 seconds later.
•
The rectifier restarts again, raising plant voltage.
•
The rectifier shuts down and restarts four additional
times.
•
During these shutdowns the Green ON LED on the
rectifier blinks, the ALM LED on the rectifier is not lit.
•
Upon the fourth shutdown, the rectifier's ALM LED
lights and the rectifier’s display indicates “HO.”
•
An external RFA office alarm is generated.
Continued on next page.