beautypg.com

VEGA VEGADIF 55 4 … 20 mA_HART User Manual

Page 66

background image

+

A

B

6

7

3

2

4

1

5

+

II

I

III

III

Fig. 66: Closed vessel
I

VEGADIF 55

II

Three-fold valve block

III

Precipitator

1

, 5 Drain valves

2

, 4 Inlet valves

6

, 7 Vent valves on VEGADIF 55

A, B Block valves

Proceed as follows to prepare for the actual adjustment:

1

F

ill the vessel to just above the lower tap

2

F

ill measuring system with medium

C

lose valve 3: Separate plus and minus side

O

pen valve A and B: Open block valves

3

V

ent plus side (probably empty minus side)

O

pen valve 2 and 4: Discharge medium on the plus side

B

riefly open valve 6 and 7, then close again: Fill the plus side

completely with the medium and remove air.

4

S

et measurement loop to operation

N

ow:

V

alve 3, 6 and 7 are closed

V

alve 2, 4 A and B are open

5

C

arry out adjustment, see end of chapter "Level measurement"

66