Gas sampling and gas conditioning technology

2-1.9.6EXME

14

STARTING

W A R N I N G !



Before starting up check whether the mains power supply
voltage corresponds with the information stated on the
nameplate.

W A R N I N G !



Start up only the built-in heated probe tube because otherwise
there is a risk of burning !

W A R N I N G !



Check whether the housing of the heating controller and the
connection box of the heated sample tube are earthed. Earth
resistance <0,3 Ohm.

Switch on mains power supply.

Then inner temperature of the sample tube has to be measured during the heat-up phase.


The maximum temperature reached is the value for the temperature class. This has to be
taken from the table below. Adjust desired temperature via controller.

N O T E !


Function and correctness of the temperature control (temperature
class) is in the sole responsibility of the installer and operator.

The nameplate contains no information about the temperature class because this is

determined by the temperature controller only.

Temperature class

Operating/sampling temperature
°C

Limiter
°C

T2

280

290

T3

185

190

T4

120

125

T5

85

90