FIGURE 2.17 100 to 120 V configuration (primary power feed, no redundant power supply)

*1 The power cable (AC#0) is connected to the PSU (PSU#0) on a one-to-one basis.

*2 This change to the power supply configuration requires a 100 V power supply for the PCI_Box, and the power

supply must be prepared separately.

*3 Use the power cable supplied with the 100 V power supply for the PCI_Box instead of the standard power cable

supplied with the device.

100 to 120 V redundant power supply configuration (primary power feed, redundant power

supply)

FIGURE 2.18 100 to 120 V redundant power supply configuration (primary power feed, redundant power
supply)

*1 Power cables (AC#0 to AC#1) are connected to PSUs (PSU#0 to PSU#1) on a one-to-one basis.

*2 This change to the power supply configuration requires a redundant power supply (100 V) for the PCI_Box, and

the power supply must be prepared separately.

*3 Use the power cable supplied with the redundant power supply (100 V) for the PCI_Box instead of the standard

power cable supplied with the device.

PRIMEQUEST 1000 Series Hardware Installation Manual
CHAPTER 2 Connection Information

37