Installing the String Monitoring Box

Page 22

Operating Instructions Powador Argus 16S DCS, 24S DCS_EN

Authorised electrician

7.6

Start-Up

Once the mechanical and electrical installation of the string monitoring box is complete and all leads have been

routed and connected in accordance with the relevant regulations, a system test can be carried out.

Checking the string monitoring box

"

To test the string monitoring box, measure the PV+ string leads against the PV- string leads, checking for

continuity.

When the string monitoring box is started up, it is necessary to start up the entire PV system as well.

NOTICE

Before starting up the entire PV system, make sure that you have read and understood the operating

and installation instructions for the inverter. Only authorised electricians who have read and fully

understood all of the safety instructions contained in these operating and installation instructions,

as well as other instructions concerning assembly, operation and maintenance, may start up this

system.

Starting up the PV system

"

Start up the PV system in accordance with the operating and installation instructions of the inverter.

Once the entire PV system has been started up successfully, the start-up of the string monitoring box is also

complete.

Closing the housing door
1. After a successful installation and start-up, close the cover using the latches on the door of the housing.