beautypg.com

7 installing the string monitoring box, Installing the string monitoring box, 7installing the string monitoring box – KACO Powador Argus 16S DCS User Manual

Page 13

background image

Installing the String Monitoring Box

Operating Instructions Powador Argus 16S DCS, 24S DCS_EN

Page 13

Authorised electrician

760

8.5

9.

5

666

Figure 4: Hole pattern

Mounting the string monitoring box
1. Unlock and open the housing door.
2. Secure the four suspension hooks to the housing from the inside using the enclosed mounting fixtures.
3. Drill holes for the fixings at the selected installation position in line with the box cut-outs.
4. Place the fixings into the holes.
5. Mount the string monitoring box to the wall using the fastening screws.

»

The string monitoring box is mounted. Continue with the installation.

7

Installing the String Monitoring Box

DANGER

Lethal voltages are still present in the terminals and leads in the string monitoring box even

after the string monitoring box has been switched off and disconnected.
Touching the leads and terminals in the string monitoring box can result in severe injury or death.
To ensure maximum protection from hazardous voltages while assembling photovoltaic systems,

both the positive and the negative leads must be fully isolated from the protective earth (PE).
Only authorised electricians approved by the supply grid operator may open and install the string

monitoring box.
Before an electrical connection is made, the string monitoring box must be mounted in a fixed

position.

Observe the safety regulations and current technical connection specifications of the responsible

power supply company.

Disconnect the DC side.

Secure it against being inadvertently switched back on.

Make sure there is absolutely no voltage present.

Do not connect the string monitoring box until the above steps have been taken.

This manual is related to the following products: