7 commissioning, 1 switching on the sunny boy, Commissioning – SMA SB 5000-US User Manual
Page 58: Switching on the sunny boy

Commissioning
SMA America, LLC
58
SB50US-80US-IA-en-37
Installation Manual
7 Commissioning
7.1 Switching On the Sunny Boy
1. Remove all covers from the PV array.
2. Switch on the AC main conductor breaker.
3. Turn the DC disconnect to position "1".
☑ The Sunny Boy performs an AFCI self-test.
DANGER
High voltages in the PV plant when exposed to sunlight.
Risk of death or serious injuries due to incorrect commissioning.
• Only commission the Sunny Boy in the following order.
• Do not insert the GFDI fuse into the Sunny Boy without a fuse holder.
AFCI self-test
Only the following types of Sunny Boy perform an AFCI self-test:
• SB 5000US-12
• SB 6000US-12
• SB 7000US-12
• SB 8000US-12
0
0
This manual is related to the following products: