All Bluetooth devices in a PV system must have the same NetID. You can use rotary switch C to set
a new NetID in the inverter before commissioning. The setting will be adopted after commissioning.
This can take up to five minutes.

Figure 12: Positions of rotary switch C

Position

Explanation

0

Communication via Bluetooth is deactivated.

1

Communication via Bluetooth with a further Bluetooth device

2 to F

NetID for communication via Bluetooth with multiple Bluetooth devices

Procedure:

1.

Danger to life due to high voltages

• Ensure that the inverter is disconnected from all voltage sources (see Section 10, page 51

).

2. To configure a new NetID, set the rotary switch

C to the determined NetID using a flat-blade
screwdriver (blade width: 2.5 mm).

7 Commissioning

SMA Solar Technology AG

Operating Manual

39

STP5-10TL-20-BE-en-13