7 Commissioning
7.1 Procedure
Before you can commission the inverter, you must check various settings and make changes if
necessary. This section describes the procedure for commissioning and gives an overview of the
steps you must always perform in the prescribed order.
Procedure
See
1.
Check which country data set the inverter is set to.
Supplementary sheet with
the default settings, type la-
bel or display
2.
If the country data set is not set correctly for your country
or your purpose, adjust to the required country data set
and the corresponding display language within the first
ten feed-in hours via the rotary switches in the inverter.
3.
If the inverter is to communicate with several Bluetooth de-
vices, or if Bluetooth is not to be used as a type of commu-
nication, configure the NetID.
4.
Commission the inverter.
7.2 Configuring the Country Data Set
A display language is assigned to every country data set. Set the country data set appropriate for
your country or purpose, with the corresponding display language, within the first ten feed-in hours
via the rotary switches in the inverter. After the first ten feed-in hours, the country data set can only
be changed by means of a communication product.
If the display language of the country data set does not match the required language, you can
change it after commissioning (see Section 8.2, page 42).
The country data set must be set correctly.
If you select a country data set which is not valid for your country and purpose, it can cause a
disturbance in the PV system and lead to problems with the grid operator. When selecting the
country data set, you must always observe the locally applicable standards and directives as
well as the properties of the PV system (e.g. PV system size, grid-connection point).
• If you are not sure which country data set is valid for your country or purpose, contact
your grid operator for information on which country data set is to be configured.