Precharged Line Routing

Do not connect the precharged tubing until all routing

and forming of the tubing is complete. See the

Coupling Instructions for final connections.
Important: CONFIRM that the correct line set

(RTEL prefix) has been provided.
1. Each set of pre-charged tubing lines contains

a 1/2” diameter liquid line and a 5/8” diameter

discharge line.

Note: The openings in the building ceiling or wall,

listed in the next step, are the minimum sizes

recommended for passing the refrigerant lines

through.
2. Have the roofing contractor cut a minimum hole

for the refrigerant lines of 2”. Check local codes,

a separate hole may be required for the electrical

power supply to the condenser.

Caution: Do NOT kink the refrigerant tubing while

routing it.
3. Route the refrigerant tubes thru the roof opening.
4. Follow straight line routing whenever possible.

Excess tubing may EITHER be coiled up INSIDE

the building OR cut out prior to connection to the

ice maker and condenser.

If the excess tubing is cut out, after re-brazing the

tubing must be evacuated prior to connection to the

ice maker or condenser.
If the excess tubing is to be coiled, spiral it

horizontally to avoid excess trapping in the lines.
5. Have the roofing contractor seal the holes in the

roof per local codes

Minimize tubing

routed outside

of the controlled

space

Best Practice: Coil

excess tubing inside

the building in a

horizontal coil.