Installing the m06228k001 or m06228k002 kit, Preparation – Gasboy Atlas Discharge User Manual
Page 5

MDE-4503 Atlas Discharge and Valve Conduit Retrofit Kit • July 2005
Page 5
Installing the M06228K001 or M06228K002 Kit
Installing the M06228K001 or M06228K002 Kit
The disassembly, replacement and reassembling process shown below is the same whether
upgrading a Single Hose System or a dual Hose System.
Preparation
1
Request permission from the manager/owner to remove power from the unit and then remove
power using normal procedures. Observe the lockout/tagout safety procedures.
Reference,
“Important Safety Information” on page 3
2
Make sure you have the proper kit type (Single or Dual Kit).
3
Be prepared to follow all applicable safety rules and procedures. Reference,
4
Using the proper tools, remove the back and front covers from the unit. Place covers in a safe
place to prevent damage or scratches. Save the mounting hardware for later reuse.
5
Follow all safety procedures and OSHA requirements as outlined in MDE-2531, Pump and
Dispenser Start-up/Service Manual. Follow Section 6, Meter Repair, under the heading
“Before Beginning Work” to bleed fuel and shut-down the unit.
Hint: place a rag into the side panels of the unit on both sides, this will keep tools from falling
into the well and getting lost.