Installing the M06228K001 or M06228K002 Kit
Page 10
MDE-4503 Atlas Discharge and Valve Conduit Retrofit Kit • July 2005
Figure 5: Installing Meter Stabilizing Bracket With Hose Retriever Details Shown
23
Ensure that the slot in the bracket (Item 2) is retrained on the stud (Item 1). Install the flanged
nut (Item 3) onto the stud. (Do not tighten.)
24
Making sure the o-ring is in place, reconnect the feedline to the manifold by inserting the (2)
retained M8x16 flanged bolts. Do not tighten.
Note: If there are two meters, repeat steps 13 to 24.
25
Tighten all (4) bolts that attach the manifold to the meter (manifold mounting screws).
26
Tighten the nut attaching the meter stabilizer bracket to the frame (Reference
, Item
3). (If there are (2) meters repeat steps 25 and 26.)
27
Tighten the (3) bolts on the meter support bracket. Repeat on the second meter if applicable.
28
Tighten the (2) feedline bolts. (If there are (2) meters repeat this step.)
If there is an internal hose retriever:
29
Remount the reel to the meter stabilizer bracket and rotate the wheel two full turns to tighten
the cable torque.
30
Re-thread the cable through the cable grommet to connect the hose and hose clamp. Repeat on
the second meter if applicable.
Continue from this point if there is not an internal hose retriever:
31
Using the copper tube (
, Item 4), slide the retained meter discharge flange on one end
of the tube so that the o-ring will be captured within the flange’s formed o-ring cavity.