r14
10
100
%
60
60
duration of the time-controlled hard blast
chilling phase (intended as a percentage of
the value established with parameter r1);
also duration of the time-controlled soft deep
freezing phase (intended as a percentage of
the value established with parameter r2)
r15
-50.0
99.0
°C/°F (1)
65.0
65.0
temperature below which the count of the
maximum
temperature-controlled
blast
chilling and maximum temperature-controlled
deep
freezing
is
started
(temperature
detected by the needle probe)
r16
0
2
- - - -
1
1
type of operating cycle that can be selected
0 = blast chilling and storage
1 = blast chilling and storage or deep
freezing and storage
2 = deep freezing and storage
r17
0.0
99.0
°C/°F (1)
5.0
5.0
"temperature detected by the needle probe -
cabinet temperature" minimum difference
such to consider the first phase of the test to
verify correct insertion of the needle probe
completed
successfully
(consider
the
difference without sign)
0.0 = the test will not be performed (neither
first or second phase)
r18
1
99
s
60
60
duration of the second phase of the test for
verification of correct insertion of the needle
probe
r19
0
1
- - - -
0
0
quick modification value during the "On"
status before starting the operating cycle
0 = work set-point during blast chilling or
during deep freezing
1 = blast chilling or deep freezing end