beautypg.com

Carrier 69NT40-511-199 User Manual

Page 106

background image

6-12

T-268-07

opening after the piston rings are compressed. A
piston ring compresser will facilitate removal. Each

piston pin is locked in place by lock rings which are
snapped into grooves in the piston wall.

1

2

3

4

5

6

7

8

9

10

1. Capscrew

2. Cap

3. Crankshaft

4. Thrust Washer

5. Rotor Drive Key

6. Connecting Rod

7. Compression Ring

8. Piston

9. Pin

10. Retainer

Figure 6-11. Crankshaft Assembly

k. Since the stator cannot be replaced in the field, the

terminal plate assembly need not be disturbed
unless a leak exists or a terminal part requires
replacing.

1

2

3

1. Equalizer Tube and Lockscrew Assembly

2. Lockwasher

3. Counterweight -- Motor End

Figure 6-12. Removing Equalizing Tube and Lock

Screw Assembly

Disassemble and assemble the terminal plate as shown
in Figure 6-13.
The terminal mounting plate assembly, as originally
installed, is assembled so as to leave a small space
between the outer terminal bushing and the surface of
the mounting plate. This is to provide further crush of
the terminal bushing in case a leak should occur. To stop

a leak, tighten the terminal bushing nut only enough to
stop the escape of gas. Do not tighten until the terminal
bushing is flush with the mounting plate. The tightening
torque used at the factory is 0.21 to 0.23 mkg (18 to 20

inch pounds) maximum to prevent damage to the plastic
parts.

12

11

10

9

7

5

3

1

2

4

6

8

6

NOTE: Parts shown are for one terminal.

1. Terminal Bushing Nut

2. Lock Washer

3. Terminal Washer

4. Outer Terminal Bushing

5. O-Ring

6. Terminal Bushing Washers (Grey)

7. Terminal Bushing Washers (Red)

8. Inner Terminal Bushing

9. Terminal Mounting Plate

10. Cover Gasket

11. Inner Terminal Block

12. Terminal Screw

Figure 6-13. Terminal Mounting Assembly

This manual is related to the following products: