2

19. Apply a generous bead of silicone to the drain collar

and surrounding area on the underside of the tub.
Secure the collar using the gasket (8) and locking nut (9)
provided. Make sure the gasket is positioned so it's flat
side contacts the underside of the tub then tighten the
lock nut.

20. Insert the overflow assembly (1-3) into the overflow

hole. Refer to drawing attached.

21. Tighten the screw (3) to secure the overflow assembly

then thread the cover (4) onto the screw. Adjust the
screw as needed so the Waterworks logo is horizontal.

22. Install the tailpiece (11) using the nylon washer (10) and

nut (12) provided. Do NOT over tighten.

23. Dry-fit the slip joint gasket into the 1 ½" hub then

measure the distance from the finished floor to the slip
joint gasket to make sure the tailpiece will fully insert
into the slip joint gasket. Cut the tailpiece as needed
and remove the slip joint gasket

WASTE AND OVERFLOW CONNECTIONS
(BELOW THE FLOOR)

24. Apply clear adhesive silicone to the outside of the slip

joint gasket then insert it into the 1 ½" hub (drain) then
apply clear adhesive silicone to the inside of the slip joint
gasket. Note the silicone will act as a lubricant then act
as a seal when it cures.

25. With the drain and tailpiece attached, position the tub

so the tailpiece passes through the hole in the floor and
slides into the 1 ½" drain hub as shown.

FINAL INSPECTION:

26. Fill the tub with water to the point where water enters

the overflow opening. Drain the tub while inspecting all
connections above and below the flooring for leaks.

27. Run a bead of tub and tile caulk around the bottom

edge of the tub where it meets the floor. Wipe away
any excess caulk with a wet paper towel.

28. Cover the bathtub surface with a bathtub liner or other

form of protection until construction is completed.

► If further assistance is required, please contact Product

Support at 1-800-927-2120 (8am-7pm EST)

8. Cover the floor with a pad or other protective material

and gently rest the tub on its side to allow for final
drain and overflow assembly.

9. Unthread the stopper (5,5a) from the drain collar then

slide the gasket (7) onto the collar then insert it into
the drain opening. A bead of clear adhesive silicone
around the drain collar can be applied instead of the
gasket.

10. Apply a generous bead of silicone to the drain collar

and surrounding area on the underside of the tub.
Secure the collar using the gasket (8) and locking nut
(9) provided. Make sure the gasket is positioned so it's
flat side contacts the underside of the tub then tighten
the lock nut.

11. Insert the overflow assembly (1-3) into the overflow

hole. Refer to drawing attached.

12. Tighten the screw (3) to secure the overflow assembly

then thread the cover (4) onto the screw. Adjust the
screw as needed so the Waterworks logo is horizontal.

13. With the drain attached, position the tub so the drain

passes through the hole in the floor.

WASTE AND OVERFLOW CONNECTIONS
(BELOW THE FLOOR)

14. Install the tailpiece (12) using the tailpiece nylon

washer (10) and nut (12) provided. Do NOT over
tighten.

15. Dry fit the remaining DWV pipe connections to the

proper dimensions. Using the 1 ½" slip joint gasket
(13) provided, connect the tailpiece to the hub.

16. Go to Step # 24.

FOR INSTALLATIONS WHERE ACCESS FROM
BELOW THE FINISHED FLOOR IS LIMITED,
I.E. SLABS:
WASTE AND OVERFLOW INSTALLATION

17. Cover the floor with a pad or other protective material

and gently rest the tub on its side to allow for final
drain and overflow assembly.

18. Unthread the stopper (5,5a) from the drain collar then

slide the gasket (7) onto the collar then insert it into
the drain opening. A bead of clear adhesive silicone

11.14.07

10. Apply a generous bead of silicone to the drain flange
collar. Apply thread sealant on drain flange threads and
bottom of tub. Secure the collar using the gasket (8),
metal washer (8a), and locking nut (9) provided. Make
sure the gasket is postioned so its flat side contacts the
underside of the tub then tighten the lock nut.

9. Remove the stopper (4,4a) from the drain collar then

12. Tighten the screw (3) to secure the overflow assembly.
Adjust the screw as needed so the Waterworks logo is
horizontal.

(11)

Empire Waste and Overflow

18. Remove the stopper (4,4a) from the drain collar then

21. Tighten the screw (3) to secure the overflow assembly.
Adjust the screw as needed so the Waterworks logo
is horizontal.

EMPIRE WASTE AND OVERFLOW (EMDR02)

19. Apply a generous bead of silicone to the drain flange
collar. Apply thread sealant on drain flange threads and
bottom of tub. Secure the collar using the gasket (8),
metal washer (8a), and locking nut (9) provided. Make
sure the gasket is postioned so its flat side contacts the
underside of the tub then tighten the lock nut.