These guidelines have been prepared for the professional contractor to aid in the installation of:
UNIVERSAL THREE WAY DIVERTER VALVE FOR PRESSURE BALANCE SHOWER SYSTEMS
STYLE No. GUDV65, GU65DV (UK).
All dimensions are based on original specification and are subject to change and variation.
Please consult your Design Associate for current specifications.

¾ You must have the pressure balance valve (GUPB81 or

GUPB87) on hand in order to install the diverter valve
(GUDV65).

1. Make sure the valve is positioned according to the

valve markings with the inlet port situated so that
mixed water flows into the inlet.

2. Rough-in the diverter valve to an appropriate depth

based on the trim being used.

3. The cartridge stem and threaded tube on the diverter

valve can be cut to various lengths depending on the
style of trim.

¾ Refer to the Installation Guidelines of individual trims

for cutting dimensions and related information.

4. After the rough-in is completed, turn on the hot and

cold supplies and check for leaks. Allow the water to
run so the lines can be flushed completely.

5. Verify all the valves are functioning properly.

MIXED WATER INLET

CARTRIDGE STEM

THREADED TUBE

6. Attach the stem extension to the cartridge stem with

the screw then install the tile guard.

¾ If further assistance is required, please contact Product

Support at 1-800-927-2120 (8am-6pm EST).


¾ See the service part document for parts ordering,

available on WATERWORKS.COM.


† BSP Adapter can be ordered separately:

(4x)

STYLE No. UNUK02

ITEM No. 45-57632-24328

STEM EXTENSION

SCREW

TILE GUARD