Installation, Step 5) fig. # 93, Fig. # 95 – EFCO 403 Series Storefront User Manual
Page 81: Step 6), Fig. # 94, Step 2), Step 4) step 3), Step 1)

EFCO CORPORATION 1/2013 PART NO. Y001
Page 81 of 94
Series 401,402, & 403 Installation Instructions
STEP 5)
Fig. # 93
GLASS STOPS
LOWER
Fig. # 95
form a gutter. See figure # 93.
Tool silicone along the end
profile of the horizontal and up
the brake metal captured legs to
STEP 6)
#STT7 (4 or 6)
FORM GUTTER
Fig. # 94
# SPZ1
Install the center vertical, if
instructions for brake metal
and top horizontal installation.
required, and refer to page
80 of the adjustable base
Apply a continuous bead of silicone to the interior gasket
STEP 2)
required. See figures # 93 and # 95 below.
as shown in figure # 93 below and marry to sealant in step 2.
Attach with # SPZ1 # 8 x 3/4" PL-PH-SMS screws as required.
Seal behind the interior half of the vertical (1G14) at the top
race of the mullions located at the area of the intermediate
thermal strut to prevent water from traveling
Apply a continuous bead of silicone over the
through the seam. Attach the bottom horizontal
to the verticals with #STT7 # 10x 1 " screws as
# STT7 (4 or 6)
UPPER
GLASS STOPS
STEP 4)
STEP 3)
horizontal. See figure # 93 below.
anchor into the opening as previously outlined.
Place preassembled frame elevation onto the sill flashing and
4 1/2" ADJUSTABLE HEIGHT
INTERMEDIATE HORIZONTAL
SECTION IV: E.
STEP 1)
INSTALLATION