Screw spline fabrication, Step 3) step 4), Step 1) step 2) – EFCO 403 Series Storefront User Manual
Page 31

EFCO CORPORATION 1/2013 PART NO. Y001
Page 31 of 94
Series 401,402, & 403 Installation Instructions
If the opening has an entrance, see the appropriate frame and
Cut horizontal glass stops to day lite openings minus 1/32".
See pages 9, 17, and 27 of the parts identification section.
NOTE: Door jambs run to the floor and are cut longer than other
(D.L.O. - 1/32")
STEP 3)
STEP 4)
Drill holes for assembly screws on vertical members.
(See Fig. # 5 page 35).
NOTE: Drill jigs are available.
Cut horizontal members to day lite openings.
(Between vertical mullions)
verticals.
door fabrication installation sheets.
When an entrance is required, screw spline joinery may be used with
ASSEMBLY SCREWS TO PREVENT GALLING AND BREAKAGE.
INSTALLATION, IT WILL BE NECESSARY TO 'WAX' THE FRAME
DUE TO THE SCREW TENSIONS REQUIRED FOR CORRECT
the screw spline door jambs only. Otherwise, shear block joinery
Measure the opening to determine the cut length of the
NOTE: Allow minimum 1/2" shim and caulk space around perimeter.
NOTE: Allow extra clearances, if necessary, to accommodate building
NOTE)
must be used to attach the side lite horizontals.
STEP 1)
STEP 2)
frame components.
Cut the verticals to frame size.
NOTE: Verticals must run through.
tolerances and building movement.
NOTE: Consult A.D.A. requirements to verify compliance.
SECTION III: A. SCREW SPLINE FABRICATION
The screw spline system is a fabrication and erection method that
permits the preassembly of single units in the shop or at the job site.
These units are then erected by mating the male mullion with the
female mullion counterpart.