Fig. # 88, Fig. # 87, Step 7) – EFCO 403 Series Storefront User Manual
Page 79: Step 6), Step 5)

EFCO CORPORATION 1/2013 PART NO. Y001
Page 79 of 94
Series 401,402, & 403 Installation Instructions
These recommendations are for general erection procedures only. For actual
job conditions, see the details on the shop drawings. For perimeter anchor
type and spacing, refer to the approved shop drawings or consult the project
design professional
.
1G14
24
" O
.C
.
as shown and attach with (4) or (6) # SPZ3 # 8 X 3/4" PL-PH-SMS
Seal behind the interior half of the verticals (1G14) at the top
as required. See figures above.
STEP 7)
Fig. # 88
1G13
SEALANT
4"
SEALANT
# SPZ1 (4 or 6)
SEALANT
mullion/jamb and up the brake metal captured legs to form a
Tool silicone along the end profile of the horizontal to the vertical
gutter. See figure # 88 below.
STEP 6)
Fig. # 87
Anchor the sill to the floor at 4" from the ends and 24" on center.
Seal over the screw heads with silicone.
4 1/2" ADJUSTABLE HEIGHT
SIDE LITE BASE INSTALLATION
STEP 5)
See figure # 88 below.
SECTION IV: E.