Commissioning

GENERAL

The following commissioning information is based on a complete matched Airedale
system using R410A refrigerant.

Pre-Start Checks

Once the whole system has been installed it is most important that the following pre-start
checks are made:-

GENERAL

1

The unit condition is satisfactory.

2

All pipework is complete and insulated where necessary.

Electrical

1

All electrical connections (both mains and control) are properly terminated.

2

The power supply is of the correct voltage and frequency.

3

External fuses/circuit breakers are of the correct rating.

4

The units are properly earthed in accordance with current regulations.

5

All pipework is earth bonded as required.

6

Check that there is a supply to the crankcase heater (if fitted) and ensure this is
switched on for a minimum of 8 hours prior to the unit operation.

Refrigeration

1

The unit condition is satisfactory.

2

All pipework is complete and insulated where necessary.

3

All fans are able to rotate freely.

4

The system has been evacuated correctly.

5

Check the operation of the high and low pressure switch settings. These should be
as follows:-

HIGH PRESSURE SWITCH - 40.25 Bar CUT OUT

LOW PRESSURE SWITCH - 0.5 Bar - CUT OUT

2.5 Bar - CUT IN

6

The low pressure switch is automatically reset. The high pressure switch must be
reset by either switching the unit off/on at the isolator, or de-energising the
compressor signal from the indoor unit.

Fan Speed / head
pressure control

The head pressure control, allows control to be achieved in ambients down to -20°C.

Defrost Control

Defrost is controlled by software (user defined) via a coil temperature sensor.