Pressure Relief Valves Adjustment Procedures


To check your relief valve setting, first disconnect the hoses. Run the operator either open or closed (the
gate will not move with the hose disconnected. The relief valve is found on the rear of the hydraulic
power unit. It has an adjusting head and lock nut. To adjust, loosen the lock nut and screw the threaded
bolt clockwise for increased pressure, counterclockwise to decrease pressure.

MODEL

FACTORY RELIEF SETTING

SwingRiser (HRG 220 ST)

1350 PSI

SwingRiser Twin (HRG 222 ST)

1350 PSI

There is only limited value in using the relief valve as an entrapment protection device. Photo Eyes or
gate edges are the best methods to protect pedestrians and maintain reserve power to reliably drive the
gate.



Maintenance Schedule

Swing Gate Operator Maintenance Schedule


Name of part

What to do

Check at these recommended monthly intervals

1

3

6

12

60

Gate and Hardware

Check for damage

*1

X

Gate post

Check for excessive wear

*2

X

Anchor bolts

Check for tightness

*3

X

Support post

Check for movement

*4

X

Limit Switches

Check normal function

*5

X

Fluid level

Check for loss of fluid

*6

X

Hydraulic fluid

Drain and replace fluid

*7

X

Clock Battery

Replace

*8

Motor Brushes (DC Only)

Replace

*9

X