1.2.2 Pad

Mount

1.

Using the dimensions shown below, locate the operator pad mount assembly as
shown.

2.

Note that when the operator pad mount assembly is properly located, the operator
output shaft (Point C) will intersect an imaginary line drawn from the gate mounting
bracket in the closed position (A1) to the gate mounting bracket in the open position
(A2).

3.

Once the location of the operator pad mount assembly has been determined,
construct a form for the concrete pad according to Figure 3. Note that the depth of
the pad is determined by soil conditions and local building codes.

4.

IMPORTANT!! Be sure that the top of the pad is level.

5.

Let the concrete cure for 48 hours before proceeding with the installation of the gate
operator.

6.

Anchor the operator pad mount assembly to the pad using eight (8) 3/8 x 3 sleeve
anchors (not supplied). It is important that the operator pad mount assembly is
located correctly on the pad so that the A1-A2 line will intersect the operator output
shaft (Point C) as shown in Figure 5.

12.00

34.00

43.00

90.0°

A1

A2

C

See Detail A

Operator

Housing

Pad Mount Mounting

Stand

20.00

3.00

35.00

Minimum side room required for shown mounting position.

A1 – A2

Line

Output

Shaft

Point

C

Detail A

1.75

Figure 5

Page

18

6300-065-E-4-08