Installation tools and equipment, Tools required, Lifting equipment requirements – Alpha Technologies Te43 User Manual
Page 22
Alpha Technologies Ltd.
057-104-C0 Rev B WC
Burnaby, British Columbia. Telephone: 604 436 5900 Fax: 604 436 1233.
Page 17 of 27
4.3
Installation tools and equipment
4.3.1 Tools Required
Insulated tools are essential for DC power system installation. Use this list as a guide:
Electric drill with hammer action
Digital voltmeter equipped with test leads
Lap top computer with Cordex communication software (not required for initial installation and test)
Various crimping tools and dies, to match lugs used in installation
Torque wrench: ¼" drive, 0-150 in-lb for battery post connections
Torque wrench: 3/8" drive, 0-100 ft-lb for system connections
Insulating canvases as required (2' x 2', 1' x 1', 3' x 3', etc.)
Insulated hand tools:
-Combination wrenches
-Ratchet and socket set
-Various screwdrivers
-Electricians knife
-
Fine tipped slot screwdrivers (“tweaker”)
-Cable cutters
Cutters and wire strippers (#14 to #22 AWG) [2.5
– 34 mm
2
].
4.3.2 Lifting equipment requirements
Hoist or crane capable of lifting 1814 kg (4000 lb)
The forklift should have a rated lifting capacity of 1814 kg (4000 lb) with a minimum fork length of 36
”
Four wire-rope slings at least 1.22 m (4') long with a capacity of 907 kg (2000 lb) each.
Four clevises.
Minimum 1.59 cm (5/8
”) diameter rope to use as a tagline to guide the enclosure while lifting.
Figure 12
– Example of an insulated tool kit