Verify Normal States
The Controller display and LEDs on Converters, shelf Alarm Cards, and Fan Shelves will illuminate when power is applied
to the system.
Step
Action
1.
System Self Check
Check for normal operation
1. Green Controller Display backlight
2. Green LEDs on each Alarm Card, each Converter, and each Fan Shelf
Every LED labeled “A”, “B”, “OK”, “FAN”, “a”, and “b”
3. No Red LEDs or displays.
Figure 22 Normal LEDs
2.
Follow the Troubleshooting section to resolve any alarm states
Verify UL Installation Compliance
Complete the final step to verify UL installation compliance.
Step
Action
1.
Test each circuit by powering an open circuit at the remote end of the wire with a QS982 output. If red lights
do not flash, there is no leakage path to ground at operating voltage. If the FLT light does not blink yellow,
there is no hard short between tip and ring.
Note: Circuit powering is usually accomplished by closing the circuit using a 5-pin protector with DC power
applied to the system.
Configure Controller
Refer to Galaxy Pulsar Edge Quick Start Guide.
Verify and edit controller parameters per site engineering instructions.
Basic Configuration:
Installation Tab:
Site ID, Site Description, System Date, System Time, and Shelf J-Code or Product Code
Network page (Settings tab, Communications group):
DHCP Client / Fixed IP Address
FTTN page (Settings tab, System group):
Alarm parameters
Complete Configuration:
Verify and edit any additional controller parameters per site engineering instructions.