Grain Systems PNEG-366 User Manual
Page 46
Grain Systems, Inc. Assumption, Ill.
46
18' Autoflow
TWO RING DOOR INSTALLATION & ACCESSORIES
Figure #54
1.) Remove inner door panels, and outer door cover. Apply double row of rope caulk along door flanges,
noting how door and bin sheets lap. The top of the door frame goes to the inside of the sidewall and the
bottom of the door frame goes to the outside of the sidewall sheet. With inner door panels and outer door
cover removed set door frame into opening. Insert a bolt at the (4) corners of door frame and sidewall,
do not tighten until completing step #2.
2.) Reinstall inner door panels at original locations. Close latch bars to lock panels in place. Be sure that panels
are fully seated over all bearing pins. Install inner panel hinge assemblies per illustration instructions with
hinges. Note: do not distort door frame with use of alignment or drift punches - if necessary, drill
or ream holes to insert bolts in door frame. Now tighten frame bolts starting at center and working
toward top and bottom on each side.
3.) Keep inner panels latched and loosen all bearing pin bolts. Retighten all bearing pin bolts.
This makes loading on pins uniform for easier operation of panels.
4.) If some latch bars are loose or require excessive force to lock, loosen hex socket capscrews and adjust
in or out until latch bars operate smoothly. Check that the panels are fully seated over all bearing pins.
5.) Re-install outer cover. Adjust outer door hinges and latches as required.
6.) Assemble door hold back as shown on next page. Open door cover until it approaches the bin wall. Hook
retaining bracket over lower latch mount and position the door hold back against bin wall in a valley. Drill
a 3/8" hole through the bin wall and bolt the door hold back to the bin.
4.00" Bin Corrugation
WD-6133 18' Bins
Before starting to install, be sure the correct door has been received.
REV. 11-20-96