beautypg.com

Figure #26 leveling band post installation – Grain Systems PNEG-366 User Manual

Page 24

background image

Grain Systems, Inc. Assumption, Ill.

24

18' Autoflow

Leveling Band Post

2nd hole from sidewall

Leveling Band Post

6th hole from sidewall

Rotary Switch

S-277

5/16" x 1.1/4"

Bin Bolt

Figure #26

LEVELING BAND POST INSTALLATION

Install the leveling band posts on the floor as shown in Figure #26.

The second and sixth holes in the beam indicate the location of the leveling band posts. Attach posts with

5/16" x 1.1/4" bin bolts (S-277). In the second hole from the bottom of the sheet, there will be 6 posts (1

every third sheet). In the sixth hole there will be 6 posts (1 every third sheet). After all of the posts have

been installed fill the unused holes with 5/16" x 1.1/4" bin bolts.

REV. 11-20-96