Hardware Installation

This section describes how to physically install the 6 10/100/1000T + 2 10/100/1000T/

100/1000 SFP Combo w/ X-Ring Managed Switch.

Installation Steps

1. Unpack the Industrial switch.

2. Check if the DIN-Rail is screwed on the Industrial switch or not. If not, please refer to

DIN-Rail Mounting section for DIN-Rail installation. If user wants to wall mount the

Industrial switch, please refer to Wall Mount Plate Mounting section for wall mount

plate installation.

3. To hang the Industrial switch on the DIN-Rail track or wall, please refer to the

Mounting Installation section.

4. Power on the Industrial switch. Please refer to the Wiring the Power Inputs section

for information about how to wire the power. The power LED on the Industrial switch

will light up. Please refer to the LED Indicators section for indication of LED lights.

5. Prepare the twisted-pair, straight through Category 5e/above cable for Ethernet

connection.

6. Insert one side of RJ-45 cable into the Industrial switch Ethernet port (RJ-45 port)

and another side of RJ-45 cable to the network device’s Ethernet port (RJ-45 port),

e.g. Switch, PC or Server. The UTP port (RJ-45) LED on the industrial switch will

light up when the cable is connected with the network device. Please refer to the

LED Indicators section for LED light indication.

7. When all connections are set and LED lights indicate normal operation, the

installation is complete.