Installation and start-up procedures 65

25A Switch Mode Rectifier

NT5C06B / C Installation and User Manual

Procedure 15 - Parallel verification

Step Action

1

It is recommended to leave the units functioning for at least 30 minutes

to reach full stability prior to final adjustment.

2

Turn all the DC breakers to the ON position.

3

Turn all the AC breakers to the ON position.

4

To achieve the system float voltage determined by the battery vendor or

the power engineer, increase the FLT potentiometer of the lowest current

rectifier, or reduce the FLT potentiometer of the highest current rectifier

to bring the system float voltage up or down respectively.
The system float voltage shall be read from the system’s meter voltage

reading.
Verify that the system float voltage level is constant while proceeding

through the next step.

5

The load share amperage for each rectifier must be equal. Adjust the

individual float potentiometer as needed to balance the current delivered

by each rectifier. It is recommended that the current from each rectifier

be at least 3 amperes (that is, 9 A for three rectifiers) for best operating

results.

–end–

Note:

Some rectifiers may still indicate an RFA (red RFA led).

A red RFA indicates a rectifier delivering less than 0.1 A.

Rotating the float potentiometer (FLT) slightly clockwise

will make the LED illuminate green.

Low voltage disconnect (LVD)

Testing and adjusting the LVD units (NT6C13FA/FH) (Circuit Pack

NT6C13PB Rel. 03).

To verify the LVA and LVD/LVDR operating levels on line, without

disconnecting the load, proceed as indicated in Procedure 16: