Chapter 4: System Administration

Understanding Failover Operations

4.2.1.2

Planned Failover in Windows Server 2008 R2

Follow these steps to perform a planned failover on a Syncro CS 9271-8i system running Windows Server 2008 R2.

1.

Create a backup of the data on the Syncro CS 9271-8i system.

2.

Open the Failover Cluster Manager, as shown in the following figure.

Figure 40 Failover Cluster Manager