Page 23 a – KACO Powador-protect User Manual
Page 23
Page 23
A
Supply
Contact load capacity on the Powador-protect
AC
250 V / 2 A inductive
DC
24 V / 8 A
Connect AC supplied tie circuit-breaker (Figure 7)
↻ You have installed 2 suitable external tie circuit-breakers
between feed-in meter and generation plant.
1. Connect "A1" connection of tie circuit-breaker 1 to terminal "14"
of the Powador-protect.
2. Connect "A2" connection of tie circuit-breaker 1 to neutral con-
ductor N of the AC voltage supply.
3. Connect terminal "11" of the Powador-protect to a phase of the
AC voltage supply.
�
The connection of tie circuit-breaker 2 is made on the same
principle (A1 to "24", A2 to "N", L1 to "21").
21
22
14
11
12
N
L3
L2
L1
A2
A1
RS485B
RS485A
GND
RS485B
RS485A
GND
CAN H
CAN L
GND
CAN H
CAN L
GND
D01
GND
DI4
DI3
DI2
DI1
24
21
J1J2J3J4
L1
L2
L3
N
L1
L2
L3
N
Figure 7: AC-supplied tie circuit-breaker, installation with wire
jumper