7 Commissioning
SMA Solar Technology AG
56
STP10-17TL-IA-en-32
Installation Manual
7 Commissioning
7.1 Commissioning the Inverter
1. Check that the device is fixed securely to the wall (see Section 5 "Mounting", page 20).
2. Check that the country configuration is correct (see Section 6.5 "Setting the Country Standard
and Display Language", page 44).
3. Check that the AC grid cable is connected correctly (see Section 6.3 "Connecting the Electricity
4. Check that the DC cables (PV strings) are connected correctly (see Section 6.4 "Connecting the
5. Close unused DC inputs with the appropriate DC connectors and sealing plugs
(see Section 6.4.4 "Connecting the PV Array (DC)", page 40).
6. Close all enclosure openings.
7. Dock the lower enclosure lid at an angle and
attach. The captive screws must protrude.
8. Pre-screw all six screws and then tighten them in the
sequence shown on the right (torque: 2.0 Nm).