3-6 PBC Pole Installation (continued)

• Mount the Sector Pole Weldment, 4 Required in at each level, at the top position on the Pole.

• Mount the Sector Pole Weldment, 4 Required in at each level, at the bottom position on the Pole.

• Ensure the Weldment are level and at the 21.5 inches spacing, See Side View PBC Pole Mounting in

Illustration 3-1.

• Check that the bolt hole's alignment matches, and the surfaces are parallel to each other.

• The PBC is now ready for rigging to lift in place with a power hoist.

• Connect the lifting Spreader Bar, with the Load -- Rated Snaps to the lifting Eyes, in the top of

Pole Mounting Plate on each side of the cabinet.

CAUTION !

• Carefully lift the PBC to the proper height to be able to slip the bottom bolts of mounting plate into the

lower Weldment nuts.

• Tighten the bolt only hand tight to permit some play while installing the top Weldment bolts.

• Tighten the all bolt’s to a torque of 28.5 ( N

2

m ) apply one drop of Torque-Seal ® to each bolt.

3-7 Power Backup Cabinet to Pole Grounding

• The details of installation of the ground connections are shown in Illustration 3-2.

• Install the ground jumper and ground cables as shown in Illustration 3-2 and Table 3-1 Ground Kit.

• Inspect the ground connection in the lower left, rear corner of the cabinet to the door at the hinge side.

TABLE 3 - 1 POLE MOUNTING CABINET GROUND KIT

ITEM DESCRIPTION

QTY

OLP

P/N

1

Compression Connector, 6 AWG, 2 Hole Lug

2

1200-182

2

M 6 x 16 mm, Screw, Hex Head, S.S.

4

1800-300

3

M 6, Washer, Split, S.S.

4

1825-085

4

M 6, Washer, Flat, S.S.

4

1825-084

5

6 AWG, Wire Stranding, Green, Grounding by 26 inches

2

4000-090

6

2 AWG, Wire Strand, Green, Grounding Buss, reference only
Contractor Supplied.

x

Contractor

Supplied

7

C-Tap, 12-1/0 Awg Burndy

2

1200-171

3-8 Power Backup Cabinet Grounding Test

• Inspect the ground jumper and ground cable connections for good crimp, shown in Illustration 3-2.

• Inspect the ground connection in both rear corners of the cabinet to the lower left, rear corner of the door

at the hinge side.

• Inspect the M 6 hex head screws for torque of 7.7 (N

2

m) compression lugs on lower rear corners.

• Inspect the Electronic Tray ground strap to the cabinet at the upper left corner of the door.

• Tighten the all bolt’s to a torque of 7.7 (N

2

m) apply one drop of Torque-Seal ® to each bolt.




19