Lift Removal
1. Disconnect all cables from the projector. It may be necessary to remove all
cabling
2. from the cable management clips on the side of the lift if disconnects were not
installed.
3. Remove the Ceiling Closure Panel.
4. Remove the projector from the lift.
5. Raise the lift into the closed position.
6. Disconnect the AC power and remote control cables.
7. Support the lift with an appropriate support system.
8. After the lift is secured, remove the mounting hardware.
9. Caution: mounting hardware may fall when removed.
10. Lower the lift from the ceiling, and crate for transport.
Maintenance & Safety
All Display Devices lifts are virtually maintenance free.
Annual safety checks are suggested to insure continued reliability and safe operation.
1. Inspect lifting cables for wear.
2. Inspect drive chain for any wear.
3. If equipped with safety strap(s), verify that they are drawing smoothly in and out
of the clutch area, and that there is no sign of wear and tear. Also check them
for proper locking operation with a quick tug on the strap(s).
4. Check motor and bearings for any leakage.
5. Verify limit switch operation.