INITIAL START-UP

4-6

4.4 UNIT REASSEMBLY

Once the combustion calibration adjustments

are properly set, the unit can be reassembled for

service operation.
1. Set the ON/OFF switch in the OFF position.
2. Disconnect AC power from the unit.
3. Shut off the gas supply to the unit.
4. Remove the manometer and barbed fittings

and reinstall the NPT plug using a suitable

pipe thread compound.

5. Remove the combustion analyzer probe

from the vent hole. Replace the NPT plug in

the vent hole using a suitable pipe joint

compound.

6. Replace the unit’s side panels and front

door.

4.5 OVER-TEMPERATURE LIMIT

SWITCHES

The unit contains both automatic and manual

reset over-temperature limit switches. These

switches are mounted on a plate attached to the

boiler shell as shown in Figure 4-5. The switches

can be accessed by removing the left side

panels of the unit. The manual reset switch is

not adjustable and is permanently fixed at

200°F. This switch will shut down and lock out

the boiler if the water temperature exceeds

200°F. Following an over-temperature condition,

it must be manually reset by pressing the

RESET button before the boiler can be

restarted. The automatic reset over-temperature

switch is adjustable and allows the boiler to

restart, once the temperature drops below its

temperature setting. Set the automatic over-

temperature switch to the desired setting.

RESET BUTTON FOR MANUAL

RESET TEMPERATURE LIMIT

SWITCH

ADJUSTABLE
TEMPERATURE
LIMIT SWITCH

MOUNTING

PLATE

ON SHELL

HIGH LIMIT

Figure 4-5

Over Temperature Limit Switch

Locations