Replacing the measuring system

Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Deutschland

Telefon +49 711 3409-0, Telefax +49 711 3409-133, E-Mail: [email protected]

41

English

7 Replacing the measuring system

The following points must be noted when replacing the measuring system:

● The new measuring system must have the same item number as the system

being replaced. Any deviations from this must be cleared with Pilz.

● You must ensure that the count direction set via hardware switches on the new

measuring system matches the previous count direction.

● The new measuring system must be installed in accordance with the

specifications and requirements stated in the chapter entitled “Assembly”.

● The new measuring system must be connected in accordance with the

specifications stated in the chapter entitled “Connection/Shield connection”.

● When recommissioning the replaced measuring system, a protected test run must

be carried out to ensure the system functions correctly.