EFCO 8800 Series Assembly Instructions Vol.5 User Manual
Page 44
![background image](/manuals/636015/44/background.png)
EFCO 2009
Page 44
Series 8700 / 8800 Unitized Curtain Wall Assembly Instructions - Volume 5
Section 25 - Captured Vent Unit Glazing at Stack Sill : A. Temporary Glazing Locators
Figure 75
1. Apply two temporary glazing locators (KV03) with isolators and setting blocks at approximate quarter points at the horizontal at the head of the vent opening
and intermediate horizontal locations.
2. Refer to Volume 2, page 20 and 21 of the S-8000 Unitized Curtain Wall Assembly Instructions for assembly details and notes.
Temporary Glazing
Locators
HEAD
SILL
Concealed Vent
opening
Intermediate
Horizontal
Concealed Vent
Stack Sill
Concealed Vent Head
Intermediate Horizontal
Concealed Vent
Head
Temporary Glazing
Locators (KV03)
KV03
KV03