Series 8700 / 8800 Unitized Curtain Wall Assembly Instructions - Volume 5
Section 22 - SSG Vent Unit Glazing at Fixed Horizontal : B. Setting and Caulking Glazing
Figure 28
Set glazing onto the silicone
spacer gaskets and against
the setting blocks at the
temporary glazing locators.
1. Set the glazing on the silicone spacer gaskets making sure glazing is pressed firmly onto the setting blocks of the temporary retainers.
2. Refer to Volume 2, pages 9 and 10 of the S-8000 Unitized Curtain Wall Assembly Instructions for assembly details and notes.
HEAD
SILL
Note:
Unit frame squareness is critical when
operable units are incorporated into
the unit. The taller the operable unit
becomes, the more important that the
frame is completely square.
Temporary Glazing
Locators (KV02)
Temporary Glazing
Locators (KV01)
Concealed Vent
opening