Side to Side (Left to Right)
This planter is also equipped with a system to level the
main frame parallel to the axle.
While the planter is factory-leveled at the time of
assembly, some misalignment may occur during shipping
and/or transport.
Note: It is easier to perform this operation with the planter
unfolded and in the fully-raised position.
1.
Measure the distance from the main frame to the
axle on both sides of the planter as far from the
center as possible, but equidistant from the center.
These distances must be equal in order for the
planter to plant evenly, and are approximately
133.6 cm (52
1
⁄
8
inches) with the planter fully raised.
If the distance is not the same from one side to the
other, use the following procedure to correct this.
2.
Loosen the ten, 1 inch bolts
holding the pin
support plates
on both sides.
3.
Loosen the jam nuts
on each of the four,
3
⁄
4
inch
set screws
located at the top and bottom of each
of the pin support plates.
To lower the left side of the planter, drive in the left
pin support plate set screw and drive out the right
support plate set screw.
To raise the left side of the planter, drive in the right
pin support plate set screw and drive out the left
plate set screw.
4.
Check the distances from the main frame to the axle
again. If they are not equal, continue adjusting.
5.
Once both sides are equal, secure the jam nuts on
both lower (left and right) set screws.
6.
Drive in the upper (left and right) set screws and
tighten the jam nuts.
7.
Tighten the 1 inch bolts securing the pin support