Roller screed assembly – Multiquip WRS5200DFPU (KUBOTA WG972-GL-E3 DUAL FUEL) User Manual
Page 34
page 34 — wrs5200dfpu hYdrauLIC roLLer sCreed • operatIon manuaL — rev. #0 (08/18/14)
roller screeD assembly
task 2: middle truss sections (reference figure 15)
1. Locate the 8 ft. (2.4 m) right-side section of truss
D.
This truss section can be identified by the RM8 marking
on the top pipe.
2. Next locate the other 8 ft. (2.4 m) left-side section of
truss
E. This truss section can be identified by the LM8
marking on the top pipe.
3. Reference detail B, and join truss sections
D and E
together. Use the 1/2-13X1-1/2 HHCS screws (12)
when assembling these
two truss sections along with
1/2-inch flat washers (24) and 1/2-inch nyloc nut (12).
task 3: middle Bracket)
Locate middle bracket P/N 16653. Place middle bracket
between 3 ft. truss section (
C) and the 8 ft. truss section
(
D) as outlined in Figure 15.
4. Use the 1/2-13X1-3/4 HHCS screws (12) when joining
truss sections
C, D and E (with middle bracket) along
with 1/2-inch flat washers (24) and 1/2-inch nyloc nut
(12).
task 4: Bearing Installation
If the strike tube bearing has not been installed onto the
middle bracket perform the following:
1. Mount strike tube bearing onto middle bracket.
2. Secure strike tube bearing with 7/16-14x2 HHSC
screws (2) and 7/16 nyloc nuts (2). Torque bearing
support nuts to 75 ft.-lbs. (102 N.m).
3. Insert splined shaft into middle mounting bracket as
shown in Figure 15.
4. Tighten bearing set screws to secure splined shaft.