page 34 — wrs5200dfpu hYdrauLIC roLLer sCreed • operatIon manuaL — rev. #0 (08/18/14)

roller screeD assembly

task 2: middle truss sections (reference figure 15)

1. Locate the 8 ft. (2.4 m) right-side section of truss

D.

This truss section can be identified by the RM8 marking

on the top pipe.

2. Next locate the other 8 ft. (2.4 m) left-side section of

truss

E. This truss section can be identified by the LM8

marking on the top pipe.

3. Reference detail B, and join truss sections

D and E

together. Use the 1/2-13X1-1/2 HHCS screws (12)

when assembling these

two truss sections along with

1/2-inch flat washers (24) and 1/2-inch nyloc nut (12).

task 3: middle Bracket)

Locate middle bracket P/N 16653. Place middle bracket

between 3 ft. truss section (

C) and the 8 ft. truss section

(

D) as outlined in Figure 15.

4. Use the 1/2-13X1-3/4 HHCS screws (12) when joining

truss sections

C, D and E (with middle bracket) along

with 1/2-inch flat washers (24) and 1/2-inch nyloc nut

(12).

task 4: Bearing Installation

If the strike tube bearing has not been installed onto the

middle bracket perform the following:
1. Mount strike tube bearing onto middle bracket.
2. Secure strike tube bearing with 7/16-14x2 HHSC

screws (2) and 7/16 nyloc nuts (2). Torque bearing

support nuts to 75 ft.-lbs. (102 N.m).

3. Insert splined shaft into middle mounting bracket as

shown in Figure 15.

4. Tighten bearing set screws to secure splined shaft.